Home> Guide
Joining machinery & electronics manufacturing industries' investment projects
(chinadaily.com.cn)
Updated: 2015-01-06
1. Sign a contact
2. Municipal development and reform commission
(1) Project: filing
(2) Materials: project application, proposal or feasibility report, approval
(3) Time limit: 3 working days
(4) Department: investment department
3. Planning bureau
(1) Items: location permission, land use permit, building permit, project approval certificate
(2) Materials
a. Location permission: approval from development and reform commissions, project proposal
Time limit: 10 working days
Department: construction land planning department
b. Land use permit: official documents for a project approval issued by the Commission of Development & Reform, a contract on transfer of the right to use State-owned land, copies of a design institute's qualification certification;
Time limit: 10 working days
Department: construction land planning department
c. Building permit: land use, State-owned land use, plan or a general arrangement, drawings
Time limit: 20 working days;
Department: construction project planning department
d. Project approval certificate: general plan and drawing of finished construction, property survey, mapping
Time limit: 10 working days
Department: regulatory supervision department
4. Land and resources bureau
(1) Items: transfer of right to use State-owned land contract, State-owned land use certificate
(2) Transfer of State-owned land use certificate, project's location, permission
Time limit: 25 working days
Department: land department
5. Environmental protection bureau
(1) Items: environmental impact assessment
(2) Materials: project approval documents from development and reform commission and Planning Bureau, environmental impact assessment from qualified unit (one e-version, two paper), technology assessment (one e-version, four paper)
(3) Time limit: 3 working days
(4) Department: environmental assessment department
6. Industry and commerce administration
(1) Items: business license
(2) Materials: stockholder IDs and copies, name check, proof of business premises
(3) Time limit: 1 working day
(4) Department: register section
7. Quality and technical supervision bureau
(1) Items: organization code certificate
(2) Materials requested: business license
(3) Time limit: 2–3 workdays
(4) Department: code office
8. State administration of taxation and Anshun local taxation bureau
(1) Items: tax registration
(2) Materials: business license, organization code certificate, fixed housing proprietary certificate, land use certificate, lease contracts, Legal representative ID and copies, capital verification report or assessment report
(3) Time limit: 1 working day
(4) Department: taxes, municipal government affairs service center
9. Industry and information committee
(1) Items: examine and approve applications
(2) Materials requested:
a. Apply in local district or county competent departments with materials;
b. Local district or county competent departments checked in the first trial;
c. The municipal industry and information committee check;
d. Confirmation of Technological Transformation Projects of Anshun
(3) Time limit: 1 – 14 working days
(4) Department: planning office
(5) This item only applies to technological transformation projects
10. Begin construction