Home> Guide

Joining planting & breeding industries' investment projects

(chinadaily.com.cn)
Updated: 2015-01-06

1. Sign a contact

2. Municipal development and reform commission

(1) Project: filing

(2) Materials: project application, proposal or feasibility report, approval

(3) Time limit: 3 working days

(4) Department: investment department

3. Planning bureau

(1) Items: location permission, land use permit, building permit, project approval certificate

(2) Materials

a. Location permission: approval from development and reform commissions, project proposal

Time limit: 10 working days

Department: construction land planning department

b. Land use permit: official documents for a project approval issued by the Commission of Development & Reform, a contract on transfer of the right to use State-owned land, copies of a design institute's qualification certification;

Time limit: 10 working days

Department: construction land planning department

c. Building permit: land use, State-owned land use, plan or a general arrangement, drawings

Time limit: 20 working days;

Department: construction project planning department

d. Project approval certificate: general plan and drawing of finished construction, property survey, mapping

Time limit: 10 working days

Department: regulatory supervision department

4. Land and resources bureau

(1) Items: transfer of right to use State-owned land contract, State-owned land use certificate

(2) Transfer of State-owned land use certificate, project's location, permission

Time limit: 20 working days;

Department: land department

5. Environmental protection bureau

(1) Items: environmental impact assessment

(2) Materials: project approval documents from development and reform commission and Planning Bureau, environmental impact assessment from qualified unit (one e-version, two paper), technology assessment (one e-version, four paper)

(3) Time limit: 3 working days

(4) Department: environmental assessment department

6. Housing and construction bureau

(1) Items: construction permit

(2) Materials: proof of payment of infrastructure facility fee and labor insurance, quality supervision receipt, environmental impact assessment, project construction report, building permit

(3) Time limit: 15 working days

(4) Department: marketing department

7. Industry and commerce administration

(1) Items: business license

(2) Materials: stockholder IDs and copies, name check, proof of business premises

(3) Time limit: 1 working day

(4) Department: register section

8. Quality and technical supervision bureau

(1) Items: an organization code certificate

(2) Materials requested: a business license

(3) Time limit: 2–3 workdays

(4) Department: code office

9. State administration of taxation and Anshun local taxation bureau

(1) Items: tax registration

(2) Materials: business license, organization code certificate, fixed housing proprietary certificate, land use certificate, lease contracts, Legal representative ID and copies, capital verification report or assessment report

(3) Time limit: 1 working day

(4) Department: taxes, municipal government affairs service center

10. Animal husbandry and veterinary bureau

(1) Items: filing

(2) Materials requested: filled in forms from relevant district or county governments

(3) Time limit: 1 working day

(4) Department: husbandry technical advice stations

11. Start construction