London Olympics likely to come in 'under budget'
Updated: 2012-02-29 13:41
(Xinhua)
|
||||||||
LONDON - The British government revealed on Tuesday that the cost of the London Olympic Games is set to be less than budgeted.
The British Government's February 2012 Olympic Quarterly Economic Report published today showed that the overall funding package for the Games remains at 9.298 billion pounds (about $14.8 billionars), with 527 million pounds of uncommitted contingency available which is likely to be unused.
At the end of last year, the government raised concerns about the budget when it increased spending on security and on the opening and closing ceremonies of the Games.
The original budget for the opening ceremony of the Games of 41 million pounds (about $64 million) was almost doubled shortly before last Christmas to 80 million pounds (about $125 million).
The budget for Games security was almost doubled as recently as last December, rising from 282 million pounds (about $443 million) to 553 million pounds, with the British armed forces heavily involved in providing specialist expertise and in supplementing manpower for security at Olympic venues.
The minister for sport and the Olympics Hugh Robertson said, "With 150 days to go to the Games, we remain on time and within budget with more than 500 million pounds (about $793 million) of uncommitted contingency remaining. This puts us in a strong position and gives me increasing confidence that we can deliver the Games under budget."
The construction program of the Olympic Delivery Authority (ODA), whose job is to build the Olympic venues for the London Organizing Committee of the Olympic Games (LOCOG), is 96 percent complete.
Dennis Hone, Chief Executive of the Olympic Delivery Authority, said, "Once again we can report that the expected final cost of the venues and infrastructure for London 2012 is down, with costs squeezed again, bringing savings now within sight of the 1 billion pounds mark."
Hone said that the ODA remain on the Olympic Park, in the Stratford district of London, to complete the parklands, roads and spectator access.
He added, "We will complete our role by working with transport operators to get spectators to venues and keep people moving, licensing and enforcing the rules for trading and advertising, concluding contracts and transforming Games-time apartments in the Olympic Village into homes for families after the athletes are gone."
The expected final cost of the ODA construction, infrastructure and transport program is 6.777 billion pounds (about $10.6 billion).
- 'Taken 2' grabs movie box office crown
- Rihanna's 'Diamonds' tops UK pop chart
- Fans get look at vintage Rolling Stones
- Celebrities attend Power of Women event
- Ang Lee breaks 'every rule' to make unlikely new Life of Pi film
- Rihanna almost thrown out of nightclub
- 'Dark Knight' wins weekend box office
- 'Total Recall' stars gather in Beverly Hills
Most Viewed
Editor's Picks
Supplies pour into isolated villages |
All-out efforts to save lives |
American abroad |
Industry savior: Big boys' toys |
New commissioner
|
Liaoning: China's oceangoing giant |
Today's Top News
Health new priority for quake zone
Xi meets US top military officer
Japan's boats driven out of Diaoyu
China mulls online shopping legislation
Bird flu death toll rises to 22
Putin appoints new ambassador to China
Japanese ships blocked from Diaoyu Islands
Inspired by Guan, more Chinese pick up golf
US Weekly
Beyond Yao
|
Money power |