Home/News

Plant installation of Lao Houay Lamphan Gnai Hydropower Station succeeds

Updated: 2013-06-26

On June 15, the installation of the plant of Lao Houay Lamphan Gnai Hydropower Station undertaken by CGGC succeeded.

The installation was carried out by a 125/32t general-purpose overhead crane with primary lifting weight of 125t, secondary lifting weight of 32t, lifting height of 22m and span of 18m, which is an important permanent equipment for installation of powerhouse electromechanical equipments and unit maintenance.

With an installed capacity of 88 thousand kilowatts, Houay Lamphan Gnai Hydropower Station is located at the boarder between Champassak and Sekong. The EPC general contracting management model is adopted for the project.

 

Links Privacy Statement Terms of Use Contact Us

Copyright@2013 China Gezhouba (Group) Corporation. All rights reserved.